Michigan State University Football Stadium
The stadium was “turned over” to E&L in May and absolutely had to be complete 3 weeks before opening day.
The Michigan State University Football Stadium was a massive undertaking. The work involved painting the entire stadium, removing and replacing the seating, completely reworking the numerous snack bars, reworking the ramps, concrete restoration, etc. The only areas untouched were the suites. The work took place 7 days a week during good and inclement weather. The stadium was turned over 2 days ahead of the established schedule deadline. With the new face lift by E&L, the Spartans season was better than the previous year.